Godolphin & Latymer School, London- New Dining, Library and 6th Form Facility

Project Manager and Contract Administrator on a new facility in the heart of the school, providing covered linkage at three levels which join three buildings together.

Extended Dining on the ground floor around a new landscaped Courtyard with two floors of Library above; the creation of a new staircase and glazed link with access to another landscaped Biology Garden 

 

Approximate construction value £4 m.

 

Commence construction July 2022 with completion in October 2023

NLCS-1.jpg
1914 - Interior Views - Atruim.jpg

North London Collegiate School, Edgware

Securing a new masterplan through the development of a hybrid planning application comprising three phases of work over a number of years.

 

Project Manager and Employers Agent for the first phase comprising:

Phase 1- Admin and an IDEAS Hub -Innovation, Design, Engineering, Art and Science - which will underpin the shift in educational focus to deliver greater integration and coherence in the STEAM fields.

Phase 2- Tractor Barn and Admin Block

Approximate construction value £10 m.

 

Commence construction January 2022 with completion in October 2023

 

IMG_3891.JPG

North London Collegiate School- Junior School

Project Manager on the design and delivery of Courtyard infill to create new ICT Suite and Library.

 

Approximate construction value £1m. Delivered January 2021

St Paul's School, Barnes, London- GTB Phase 1 and 2

Project Manager and Contract Administrator on the delivery of a new general teaching block (GTB). This was delivered in two separate contracts using a traditional contract with a combined contract sum of circa £45m.

Phase 1 was handed over in October 2017 and Phase 2 completed in February 2020.

SPS Staff Housing1.jpg

St Paul's School, Barnes- Staff Housing

Project Manager on the design (to RIBA Stage 3) and securing of planning approval of staff housing.

The project comprises 8 x 1-bed teachers flats and 4 x 3-bed graduate flats

St Paul's School, Barnes, London- School Masterplan

Managing the new Masterplan for the school and its revised S73 planning application with the appointed consultants. Agreeing a development programme and establishing the new budget.

The revised planning application was submitted in January 2018 and received approval in May of that year.

St Paul's Girls School, Hammersmith

Assisting the school on their ambitious development proposals and upgrade of their existing school.

Review current design proposals against the changing needs of the school and how best to deliver capital spend on constrained site whilst integrating backlog maintenance.